Inspection Type |
Referral
|
Scope |
Partial
|
Safety/Health |
Safety
|
Close Conference |
2017-03-23
|
Emphasis |
L: FORKLIFT
|
Case Closed |
2018-09-27
|
Related Activity
Type |
Referral |
Activity Nr |
1198019 |
Safety |
Yes |
|
Type |
Inspection |
Activity Nr |
1219666 |
Safety |
Yes |
|
Violation Items
Citation ID |
01001A |
Citaton Type |
Serious |
Standard Cited |
19260020 B01 |
Issuance Date |
2017-04-10 |
Abatement Due Date |
2017-05-04 |
Current Penalty |
3803.0 |
Initial Penalty |
3803.0 |
Final Order |
2017-05-18 |
Nr Instances |
1 |
Nr Exposed |
1 |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.20(b)(1): The employer did not initiate and maintain such programs as may be necessary to comply with this part. a) On or about March 23, 2017, and at times prior thereto, the employer had not developed and/or implemented an accident prevention program to address hazards to which their employees and/or the employees of subcontractors are exposed. Hazards include but are not limited to falls from the lack of use of fall protection, stairs without hand railing, pneumatic nail guns without the use of safety glasses, electrical shock from damaged electrical cords, 4-way junction boxes not properly mounted with broken outlets and missing knockouts, floor holes and/or overhead hazards. Note: Abatement certification and documentation ARE required for this item. |
|
Citation ID |
01001B |
Citaton Type |
Serious |
Standard Cited |
19260020 B02 |
Issuance Date |
2017-04-10 |
Abatement Due Date |
2017-05-04 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2017-05-18 |
Nr Instances |
1 |
Nr Exposed |
6 |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.20(b)(2): The employer did not initiate and maintain a safety program which provides for frequent and regular inspections of jobsites, materials, and equipment to be made by a competent person: a) On or about March 23, 2017, and at times prior thereto, the employer did not perform effective frequent and regular inspections of sites that they controlled to identify, correct and/or eliminate hazards to which their employees and/or the employees of subcontractors were exposed. Hazards include but are not limited to falls from the lack of use of fall protection, stairs without hand railing, pneumatic nail guns without the use of safety glasses, electrical shock from damaged electrical cords, 4-way junction boxes not properly mounted with broken outlets and missing knockouts, floor holes and/or overhead hazards. Note: Abatement certification and documentation ARE required for this item. |
|
Citation ID |
01001C |
Citaton Type |
Serious |
Standard Cited |
19260021 B02 |
Issuance Date |
2017-04-10 |
Abatement Due Date |
2017-05-04 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2017-05-18 |
Nr Instances |
1 |
Nr Exposed |
6 |
Gravity |
10 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.21(b)(2): The employer did not instruct each employee in the recognition and avoidance of unsafe conditions and the regulations applicable to his work environment to control or eliminate any hazards or other exposure to illness or injury. a) The employer did not provide adequate instruction for employees in methods to control and/or eliminate workplace hazards. Hazards include but are not limited to falls from the lack of use of fall protection, stairs without hand railing, pneumatic nail guns without the use of safety glasses, electrical shock from damaged electrical cords, 4-way junction boxes not properly mounted with broken outlets and missing knockouts, floor holes and/or overhead hazards. Note: Abatement certification and documentation ARE required for this item. |
|
Citation ID |
01002A |
Citaton Type |
Serious |
Standard Cited |
19260501 B13 |
Issuance Date |
2017-04-10 |
Abatement Due Date |
2017-04-14 |
Current Penalty |
2716.0 |
Initial Penalty |
2716.0 |
Final Order |
2017-05-18 |
Nr Instances |
1 |
Nr Exposed |
2 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.501(b)(13): Each employee engaged in residential construction activities 6 feet (1.8 m) or more above lower levels was not protected by guardrail systems, safety net system, or personal fall arrest system: a) Jobsite: On or about March 23, 2017 and at times prior thereto, the controlling employer did not ensure sub-contracted employees were protected while performing framing activities, which included roof sheathing, on a 8 in 12 pitched roof,without a fall protection system in place. Sub-contracted employees were exposed to fall hazards ranging from 9 and a half feet at the eaves, to over 25 feet at the roofs peak. Note) Certification of corrective action is required for this item. |
|
Citation ID |
01002B |
Citaton Type |
Serious |
Standard Cited |
19260503 A02 III |
Issuance Date |
2017-04-10 |
Abatement Due Date |
2017-05-04 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2017-05-18 |
Nr Instances |
1 |
Nr Exposed |
5 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.503(a)(2)(iii): The employer did not assure that each employee had been trained, as necessary, by a competent person qualified in the use and operation of guardrail systems, personal fall arrest systems, safety net systems, warning line systems, safety monitoring systems, controlled access zones, and other protection to be used: a) Jobsite: On or about March 23, 2107 and at times prior thereto, the Controlling contractor was not capable of identifying existing and/or predictable hazards in the surroundings or working conditions to ensure sub-contracted employees were protected from fall hazards while performing framing activities on a 8 in 12 pitched roof without a fall protection system in place. Note) Certification of corrective action is required for this item. |
|
Citation ID |
01002C |
Citaton Type |
Serious |
Standard Cited |
19261052 C01 I |
Issuance Date |
2017-04-10 |
Abatement Due Date |
2017-04-14 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2017-05-18 |
Nr Instances |
1 |
Nr Exposed |
3 |
Gravity |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1926.1052(c)(1)(i): Stairways having four or more risers or rising more than 30 inches (76 cm), whichever is less, were not equipped with at least one handrail: a) Jobsite: On March 23, 2017 and at times prior thereto, the controlling contractor did not ensure sub-contracted employees performing framing activities using a permanent stairway had a handrail in place for access to the upper levels. Note) Certification of corrective action is required for this item. |
|
Citation ID |
02001A |
Citaton Type |
Other |
Standard Cited |
19030019 C01 |
Issuance Date |
2017-07-17 |
Abatement Due Date |
2017-08-10 |
Current Penalty |
305.0 |
Initial Penalty |
305.0 |
Final Order |
2017-09-05 |
Nr Instances |
1 |
Nr Exposed |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1903.19(c)(1): The employer did not certify to OSHA, within 10 calendar days after the abatement date, that the cited violation had been abated: a) The employer did not provide certification of corrective action for citation 1, items 2a, 2b, and 2c. Citations were issued April 10, 2017 with an abatement date of April 14, 2017, and became a final order on May 18, 2017. NOTE: Abatement certification is required for this item. |
|
Citation ID |
02001B |
Citaton Type |
Other |
Standard Cited |
19030019 D01 |
Issuance Date |
2017-07-17 |
Abatement Due Date |
2017-08-10 |
Current Penalty |
0.0 |
Initial Penalty |
0.0 |
Final Order |
2017-09-05 |
Nr Instances |
1 |
Nr Exposed |
5 |
FTA Current Penalty |
0.0 |
Citation text line |
29 CFR 1903.19(d)(1): The employer did not submit to the Agency documents demonstrating that abatement is complete for each willful or repeat violation and for any serious violation for which the Agency indicates in the citation that such abatement documentation is required. a) The employer did not provide documentation demonstrating corrective action for citation 1, items 1a, 1b, and 1c. Citations were issued April 10, 2017 with an abatement date of May 4, 2017, and became a final order on May 18, 2017. NOTE: Abatement certification is required for this item. |
|
|